Wellington Yard and Maintenance Facility Improvements 89% Complete

Updated on May 4, 2022

As part of the MBTA’s Capital Transformation, the Orange Line Transformation (OLT) team has made substantial progress at the Wellington Yard and Maintenance Facility.

Read the May 4 press release about construction progress

Video Transcript

Crews continue to work diligently at Wellington Yard. Since the project began, the Orange Line team has replaced over 4 miles of track and 55 units of special trackwork.

Currently, crews are replacing ductbanks and installing electrical components such as traction power cable, signal connections, and more. Here you can see crews demolish the crossing between the mainline and Wellington’s South Yard, one of the primary entrances for vehicles. New track, ties, ballast, and third rail will also be installed giving the yard an overall rehabilitation to accommodate the new Orange Line fleet.

Stay tuned for more updates from the Orange Line Transformation team!

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Contact Us

For questions or comments related to this project, please email the Orange Line Program team at OLT@mbta.com.

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects